Wet weather has delayed the opening of the new university footbridge over Quarry Road. The bridge is now in place, but staff estimate a further week before the approach paths are laid.
Delivery of the bridge itself was put back due to heavy rain as the police delayed the over-sized motorway convoy. Since then, the bridge has been installed but groundworks and concreting has understandably taken longer. The new bridge is higher to avoid tall vehicle strikes, but this means that the approach paths need to be re-graded. With drier weather forecast, this work is expected to be completed this week.
In a conversation with Cllr Coombes providing the revised information, the bridge project director apologised for the delay. Meanwhile the Vice-Chancellor is taking no chances and has arranged the formal opening ceremony for mid October.